Source-linked public reporting

Kirksville public reporting hub

Public records, official reports and documented news leads—organized by what happened, what remains open and where the receipt came from.

Independent reporting—not a government website.

The Reporter consolidates and summarizes sources for public use. Each linked original remains the controlling record. A missing item means “not located or not yet indexed,” not “does not exist.”

Track every move

Development watch

Local, county and statewide decisions that may affect this community, with the current stage, next action and source receipt kept together.

Solar

Adair County — AES Morris Solar marked operational after 2025 construction

AES currently describes Morris Solar as operational and labels 2025 as its operating-phase year; the company lists 250 MW planned capacity. Adair County's January 31, 2025 report described construction nearing completion and anticipated testing in May. This reconciles the earlier construction-only baseline with a now-operational plant, but these sources do not fix an exact commercial-operation date or verify the final as-built capacity. AES projects $8.8 million in local tax revenue; that is a company forecast, not audited receipts. AES also describes more than 340 jobs during peak construction, not ongoing permanent jobs.

Area
Near Troy Mills east of Missouri Highway 3, extending south toward Kirksville Regional Airport, Adair County, Missouri
Decision stage
AES currently identifies operational facility; exact commissioning day and as-built capacity not independently confirmed
Next dated action
Date not stated in the source
What to watch next

Check federal EIA-860M generator-level operating month and capacity; reconcile actual county tax receipts, land-title/lease arrangements, retained jobs and restoration requirements. No new hearing or participation deadline verified.

Verification notes

PRIMARY SOURCE (DEVELOPER) — AES current project page, consulted November 20, 2026, labels the project 'operational', lists 2025 as operations period and 250 MW as 'planned capacity'. It states $8.8M expected taxes, peak construction >340 jobs, neither audited outcome. PRIOR GOVERNMENT POST — Adair County January 31, 2025 nearing-completion report https://adaircountymissouri.com/morris-solar-project-nearing-completion/ places project near Troy Mills, extends toward Kirksville airport, reported ~1,100 acres and hoped-for spring testing. EIA 860M inventory is available at https://www.eia.gov/electricity/data/eia860m/ but the exact plant row was not independently inspected in this maintenance pass. Distinguish operation asserted by AES from confirmed commissioning date, output, ownership/leases, cash tax receipts or employment. BACKLOG CORRECTION — older project milestone incorporated November 20, 2026; not a new November approval or construction start.

Open primary receipt ↗
Wind

Adair County — High Prairie turbine collapse reported west of Willmathsville October 24

KTVO reporting dated October 24, 2026 (republished by National Wind Watch October 25) describes a High Prairie turbine collapse west of Willmathsville in Adair County. The report attributes to Ameren Missouri a response securing the site, no reported injuries and an ongoing assessment. Incident cause, the turbine model, investigation conclusions, repair costs and any operating restrictions were not independently established from a regulator or direct operator document.

Area
High Prairie Renewable Energy Center, near Route A west of Willmathsville, Adair County, Missouri
Decision stage
Local television-reported turbine collapse; operator assessment reported; official findings unavailable
Next dated action
Date not stated in the source
What to watch next

Check any direct Ameren incident release, county emergency/road records and regulatory/engineering findings for cause, safety response, remedies and current operations. No confirmed hearing or comment deadline.

Verification notes

ATTRIBUTED REPORTING: Original KTVO Oct 24 2026, syndicated archived on National Wind Watch Oct25, checked Nov19 2026. Original ktvo.com page restricted; primary company incident report not available. Do not treat secondary quotation as government-certified investigation or claim precise collapse time based only on residents' sound reports. This is a separately reported Adair incident, not the earlier Schuyler collapse. Potential implications for nearby farmland, public safety, wind generation, access and insurance, but no verified economic loss, root cause, enforcement action or turbine-level repair outcome. Older incident incorporated Nov19.

Open primary receipt ↗
Solar

Adair County — Citrine Solar 40-MW proposal and county-documented Pasture Lane road work

Azimuth Renewables describes the Citrine Solar project as a proposed 40-MWac photovoltaic facility on 317 acres of agricultural/wooded land in Adair County, 304 acres of which would be fenced. Official Adair County minutes of April 16, 2025 place the project on Pasture Lane and record discussion of road protections, decommissioning and possible Chapter 100 bonds without action. September 21, 2026 county minutes report commissioners checking Pasture Road for Citrine Solar work. This establishes county-observed project-related road activity, not completed facility construction, operation, permit approval or executed financial incentives. The developer page still projects completion by December 2025; that forecast is outdated and must not be treated as achieved. Projected taxes above $5 million are developer estimates, not receipts.

Area
Pasture Lane/Pasture Road area, Adair County, Missouri; precise project parcels and land rights not verified
Decision stage
Developer-announced 40-MW solar project; project-related road work noted by county September 21, 2026; commercial operation, county approvals and payments unverified
Next dated action
Date not stated in the source
What to watch next

The publicly posted April 29, 2026 county minutes do not record a Citrine road-use approval, despite a secondary site asserting one. Seek an executed county agreement/order if it exists; separately identify Birch Creek Energy’s April 1 Pasture Lane proposal and the three unnamed solar-project leads mentioned April 20. Check permits, easements, leases, grid studies and operation notices. No current hearing or comment deadline established.

Verification notes

PRIMARY: Adair County Commission Sept 21 2026 meeting minutes page 184 (https://adaircountymissouri.com/wp-content/uploads/2026/10/September-2026-Minutes.pdf) reports site visit checking Pasture for Citrine Solar work (minutes say Citrone, likely misspelling: project identity established independently by developer and earlier minutes). PRIMARY: Adair County Commission Apr 16 2025 minutes page 517 https://adaircountymissouri.com/wp-content/uploads/2025/05/April-2025-Minutes.pdf discussed Pasture Lane, road-use/decommissioning and potential Chapter 100; explicitly no action. DEVELOPER: Azimuth https://azimuth-renewables.com/citrine-solar/ says 40 MWac, 317-acre tract, 304 fenced acres and projected >$5m taxes, outdated Dec 2025 projected completion. ATTRIBUTED secondary Civic IQ https://civiciq.com/public-contract/9ae11bbc-7b86-4feb-9f71-cf504756a99e says county approved a road-use agreement April 29 2026, but original Apr 29 minutes and signed terms have NOT been inspected: do not report confirmed approval. Actual land sale, lease, option, permit, road-use conditions, tax impact, road restoration, decommissioning security and operation unknown. Older county-source evidence incorporated Nov 18 2026, not a new Nov 18 approval. PRIMARY RECONCILIATION 2026-11-18: Official Adair County Commission April 2026 minutes, https://adaircountymissouri.com/wp-content/uploads/2026/05/April-2026-Minutes.pdf , PDF pages 1 (Apr 1), 9 (Apr 20), 14-15 (Apr 29). April 1 discusses a Birch Creek Energy road-use agreement for private access road and limited Pasture Lane substation traffic; county attorney was reviewing and no acceptance recorded that date. Relationship to Citrine Solar is NOT established; avoid conflation. April 20 discusses 3 other anticipated Adair County solar projects, unnamed, and possible school finance effects; not proof of three filed proposals. April 29 entry lists no Citrine Solar road-use vote or approval. This CONTRADICTS the secondary CivicIQ claim of an Apr 29 approved agreement as far as the published original minutes go; absence of minutes reference is not definitive proof no agreement exists elsewhere. No land sale, lease, option or project completion established. Verified primary-source reconciliation adds no newly occurring Nov 18 action.

Open primary receipt ↗
Transmission

DZTM 345-kV corridor — PSC-approved route; Adair County road and easement negotiations

The Missouri PSC order of July 16, 2025 (effective August 15) granted Ameren Transmission Company of Illinois a conditional CCN for the Denny–Zachary–Thomas Hill–Maywood (DZTM) project, including the Denny–Zachary double-circuit route. It permitted a future transfer of an undivided 49% asset interest to the Missouri Electric Commission, but does not prove the transfer occurred. Adair County Commission minutes of September 15, 2026 record statements from Ameren representatives that all Denny–Zachary easements except one in Sullivan County had reportedly been signed, clearing was expected November 2026–January 2027 and construction in 2027. A county road-use agreement, $70,000 protection escrow, dust control and NEMO Fairgrounds haul routes were discussed, not approved or funded in these minutes. No current clearing, complete easements, filed condemnation outcome or signed road agreement is verified. Macon Chronicle reporting dated October 6 says ATXI filed a third Macon County condemnation petition on October 5, 2026 (case 26MA-CC00064), seeking permanent easements over 16 parcels, alongside two August petitions. This is attributed reporting about a petition, not independently verified court relief, an executed easement, or judgment.

Area
Northern Missouri route across ten counties, including Denny substation (DeKalb), Zachary near Kirksville (Adair), Thomas Hill (Randolph) and Maywood near Palmyra (Marion); September 2026 local road-use discussion in Adair County.
Decision stage
PSC CCN authorized in 2025; Sept 2026 county discussions official; Oct 2026 Macon condemnation petitions attributed to local court reporting; judgment/construction unverified
Next dated action
Date not stated in the source
What to watch next

Verify Macon County Case.net docket outcomes in 26MA-CC00054, 26MA-CC00055, 26MA-CC00064 (including Nov 4 proceedings); check negotiated vs condemned easements, adopted road-use terms, actual construction and county fiscal impacts.

Verification notes

PRIMARY: Missouri PSC EA-2025-0087, Order Granting CCN July 16 2025, effective Aug 15; https://efis.psc.mo.gov/Document/Display/839713 (pages 1-7 and Appendix A). PRIMARY county record: Adair County Commission minutes Sept 15 2026, page 182 https://adaircountymissouri.com/wp-content/uploads/2026/10/September-2026-Minutes.pdf . Utility confirms ten county geography and expected 2027–29 timetable https://www.ameren.com/reliability/transmission/northern-missouri . ATXI and Ameren are not the same legal entity. The PSC authorization allows transfer to MEC, not proof of execution. Commission minutes establish what was said, not signed easements, construction start, adopted escrow or agreed route terms. Potential documented benefits are grid reliability and capacity; potential land, road and utility-cost implications require executed terms and cost allocation. Existing public Zachary–Locust Creek cooperative corridor entry is related but distinct, not a duplicate. Older official records newly incorporated 2026-11-18, not a new Nov 18 project approval. ATTRIBUTED REPORTING (secondary, not yet matched to original publicly accessible court docket): Macon Chronicle October 6 2026 https://maconchronicle.com/ameren-transmission-company-files-3rd-macon-county-condemnation-suit/ reports cases 26MA-CC00054 (Aug 10), 26MA-CC00055 (Aug 28), 26MA-CC00064 (Oct 5) and 16 parcels in the third case. Do not list defendant names or imply the judge granted condemnation. The reported existing 100-ft vs sought 150-ft easement rights require the instruments. Court outcome, negotiation history, landowner compensation and November 4 proceedings have NOT been independently verified. Backlog reconciliation November 19, 2026.

Open primary receipt ↗
Wind

Adair and Schuyler — High Prairie wind center seeks new 30-year federal wildlife permit

Ameren Corporation's Form 10-Q filed November 6, 2026 confirms that Union Electric Company d/b/a Ameren Missouri applied to the U.S. Fish and Wildlife Service in March 2026 for a new 30-year federal permit supporting continued operations at the High Prairie wind facility in Adair and Schuyler counties. The current permit expires in May 2027. Ameren says nighttime operations have been curtailed April–October since 2021 for protected species, and explicitly states approval of the new application is uncertain. The complete 2026 application and any changed permit terms have not been independently reviewed; filing does not equal approval.

Area
High Prairie Renewable Energy Center, Adair and Schuyler counties, Missouri
Decision stage
March 2026 federal permit application disclosed; USFWS approval or revised operating conditions unverified
Next dated action
Date not stated in the source
What to watch next

Monitor USFWS for the application/decision and any Federal Register comment period ahead of current permit's May 2027 expiry. No verified current project-specific hearing deadline.

Verification notes

PRIMARY SOURCE: Ameren Corporation Form 10-Q for quarter ended September 30, 2026, filed November 6, 2026, environmental matters (High Prairie), https://www.sec.gov/Archives/edgar/data/1002910/000100291026000032/aee-20260930.htm . Supplemental USFWS collection: https://www.fws.gov/library/collections/high-prairie-renewable-energy-center . Corporate report establishes application in March 2026 but not specific day; event_date deliberately NULL. Older application newly incorporated into public site November 17, 2026. Potential consequences: balance wind generation and protected bat conservation, nighttime curtailment, mitigation costs and future electricity production, none established outcomes.

Open primary receipt ↗
Transmission

Adair and Sullivan — Zachary–Locust Creek 33-mile co-located 161/345-kV transmission corridor

Northeast Missouri Electric Power Cooperative and NW Electric Power Cooperative's October 2025 factsheet describes a 33-mile route from Zachary Substation south of Kirksville (about 15 miles in Adair County) to Locust Creek Substation west of Milan (about 18 miles in Sullivan County), sharing a corridor with Ameren Transmission Company of Illinois (ATXI). Proposed double-circuit steel monopoles support a cooperative 161-kV line and ATXI 345-kV line. The document specifies overlapping cooperative 100-foot and ATXI 150-foot easements, for a maximum combined corridor width of 150 feet (not 250). Construction is dependent on ATXI's schedule and not independently confirmed begun.

Area
Zachary Substation south of Kirksville, Adair County, to Locust Creek Substation west of Milan, Sullivan County, Missouri
Decision stage
Coordinated utility design and easement acquisition period; actual signed easements and current construction status unverified
Next dated action
Date not stated in the source
What to watch next

Verify current route parcels, executed easements versus offers, revised construction schedule, landowner meetings, restoration conditions and utility rate impacts.

Verification notes

PRIMARY utility source: 'Zachary to Locust Creek Transmission Project', October 2025 factsheet, pages 1–2. Older official evidence newly incorporated November 17, 2026. Official page https://www.northeast-power.coop/zachary-locust-creek. Cooperative project is related to ATXI's 345-kV proposal but the October factsheet is not itself proof of final ATXI authorization or completed easement awards. Utility claims possible reliability, land-footprint and tax benefits; specific compensation, tax receipts, jobs and cost pass-through not independently confirmed.

Open primary receipt ↗
Other

Corporate energy projects: Ameren Missouri, Vestas connections and labor-origin gaps

Ten additional energy-project research files are available at https://greentopreporter.com/project-labor: High Prairie and Atchison wind; Huck Finn solar, Split Rail, Vandalia and Bowling Green solar; Big Hollow, Castle Bluff, Huck Finn and Millcreek battery storage. Capital reports High Prairie hauling and ready-mix work with Blattner as client. Invenergy documents Atchison construction and a Vestas equipment connection, without establishing the full installation or service workforce. Worker home-state totals, local-hire shares, full subcontract rosters and permanent relocation counts remain unresolved. Ameren reports about 250 Huck Finn solar peak construction jobs while EDF reports more than 500; this discrepancy is displayed rather than resolved by assumption. Solar and battery labor evidence is kept separate.

Area
Decision stage
Documented project identities and attributed contractor roles; workforce-origin investigation open
Next dated action
Date not stated in the source
What to watch next

Continue existing daily research: PSC filings, executed contracts, legal employers, union locals and aggregate workforce origins; reconcile job-count and contractor-date discrepancies.

Verification notes

Checked October 6, 2026. Claim-level receipts in lib/energy-project-labor.ts and the public tracker. Reviewed Ameren wind/solar/battery directories, Capital High Prairie portfolio, Invenergy Atchison training account and EDF Huck Finn operations release. These are company statements, not audited payroll or executed contractor rosters. No inference of worker residence from company bases or equipment brands. Daily follow-up saved to existing automation; no contacts made.

Open primary receipt ↗
Other

Project labor and contractors: unions, company roles and workforce-origin gaps

Initial source-backed labor records cover Google’s Hunt Midwest campus, Meta’s Kansas City data center and Swan Energy Center. IBEW Local 124 describes participation at Meta and Google; independent reporting attributes participation to Laborers Local 264. Project statements identify JE Dunn, Turner and Blattner in distinct construction roles; Global Earthwork & Underground reports Project Velvet experience. Company headquarters are separated from worker residence. No reliable project-level home-state totals, complete executed subcontract rosters or permanent relocation counts have been verified. Construction headcount, projected operational jobs, local training, traveling assignments and permanent moves are kept distinct. Full findings and receipts: https://greentopreporter.com/project-labor

Area
Multiple Missouri projects; directory A–Z
Decision stage
Initial documented findings; workforce origins and contract tiers unresolved
Next dated action
Date not stated in the source
What to watch next

Continue statewide project labor research through the existing daily research task. Retrieve published contracts, subcontract awards, union reports and aggregate workforce disclosures. Distinguish temporary traveling crews and permanent relocation; protect individual worker privacy.

Verification notes

Checked October 6, 2026. Read /project-labor and lib/project-labor.ts for dated claim-level sources and caveats. Company statements, union statements and independent reporting are labeled. No contact with employers, officials or unions in this review. No home states inferred from headquarters, local jurisdiction or worker identity. A travel advertisement does not prove site staffing or relocation.

Open primary receipt ↗
Data Center

Who wrote Missouri’s data-center rules? Shared wording, documented preparers and open origins

Kirksville’s September 16, 2026 staff report names Diane Albrecht, City Planner, as preparer and credits staff research, Planning and Zoning recommendations, Council discussion, City Attorney and Missouri Municipal League input. Distinctive portions of its draft appear in records from Branson, Brentwood, Cass County, Festus, Joplin, Perryville and Warrensburg. Branson’s October 8, 2024 terminology amendment reproduces the engineer-report wording; Plano’s 2025 compilation attributes an earlier shorter definition to Ordinance 2010-10-15. These records establish shared wording, not one original author or a complete transmission chain. The site’s earlier summary has no named author record. Full dated comparison and source receipt: https://greentopreporter.com/research/data-center-language

Area
Multiple jurisdictions; comparison is alphabetical
Decision stage
Documented wording; original authorship unresolved; Kirksville draft is not verified enacted
Next dated action
Date not stated in the source
What to watch next

Trace Branson Bill 6472 / Ordinance 2024-0071 and original staff drafts, MML conference handouts and comments, Plano ZC2010-05, and dated Kirksville revisions. Follow-up assigned to existing daily research task; no contacts or records requests authorized.

Verification notes

Checked October 6, 2026. Comparison and eleven primary-source links are preserved at /research/data-center-language. Earlier occurrence and matching language do not prove direct copying, improper influence, or original authorship. Separate report preparer, clause author, sponsor, approver and site synthesis. Pending adoption is labeled.

Open primary receipt ↗
Data Center

Kirksville data-center zoning: Chapter 44 draft under review

The City Council resolved on July 27 to develop data-center zoning standards. City staff then published proposed Chapter 44 revisions for the September 16 Planning and Zoning hearing, including a proposed special-use permit process. The proposal applies to Kirksville city limits only. The city said on July 28 that no data-center proposal had reached City Hall; the September 16 staff report likewise reported no developer approach. The draft is not an enacted ordinance or a project approval. The September 16 recommendation or vote has not been verified from city minutes, and the September 28 Council agenda does not list a data-center zoning action.

Area
Kirksville city limits; no project parcel established
Decision stage
Proposed zoning text; September 16 hearing outcome unverified; Council adoption unverified
Next dated action
Date not stated in the source
Verification notes

Primary sources: July 28 city notice https://public.alertsense.com/content/1911/186329 ; September 16 official draft and staff report https://www.kirksvillecity.com/Home/DownloadDocument?docId=e5d287cf-cbff-477a-92a3-64aa69ddc08e ; special-meeting agenda https://www.kirksvillecity.com/Home/DownloadDocument?docId=57e08168-a481-4d48-bfdc-d74726ddaad9 ; official P&Z archive https://www.kirksvillecity.com/p/planning-zoning-commission had no September 16 minutes as checked September 28; September 28 Council agenda https://www.kirksvillecity.com/Home/DownloadDocument?docId=2e6dc6bb-8f3d-4cf0-8930-5dafa9d0e89a did not list zoning. No verified limits or enforceable conditions on water, noise, roads, decommissioning or reporting should be inferred from a draft.

Open primary receipt ↗
Data Center

Adair County passes resolution to review data-center and large-facility standards

On September 1, the Adair County Commission passed Resolution 2026-1 declaring an intent to review possible standards for large-scale technology and renewable facilities, including data centers and cryptocurrency facilities. The county says it has no zoning regulations for development of large-scale facilities to meet technology needs. The review topics include districts, setbacks and scale, screening, noise, water conservation, electrical coordination, backup generators and fuel, traffic and construction, and safety. No numeric limits, ordinance, permit, application or project approval were adopted in this resolution.

Area
Adair County, Missouri — county action concerning potential regulation of unincorporated land; city-limit zoning is separate
Decision stage
Resolution passed — potential standards under review; no zoning rule enacted
Next dated action
Date not stated in the source
What to watch next

Watch for the Commission’s actual draft standards, public notice and hearing, recorded vote, and any adopted rule. Check whether future text makes water, noise, roads, setbacks, farmland, decommissioning security, reporting and enforcement enforceable. This resolution states no next hearing or comment deadline.

Verification notes

Verified from the county’s official posting and linked Resolution 2026-1 PDF on September 28, 2026. The source names no developer, parcel or site and imposes no measurable noise or water limit, road obligation, decommissioning bond, monitoring or complaint process. Do not apply the county review to Kirksville or Greentop city zoning.

Open primary receipt ↗
Other

Missouri is revising baseline industrial-stormwater permit conditions — comments due Aug. 30

Missouri DNR has published draft Standard Conditions Part 4 for NPDES permits addressing industrial stormwater requirements. DNR says standard conditions are minimum conditions applicable to NPDES permits unless superseded by permit-specific requirements or not relevant to the facility. The proposal incorporates Missouri and federal industrial-stormwater requirements and remains tentative during the public-comment period through Aug. 30, 2026. This is statewide permit-policy context, not evidence that a specific Greentop business or proposed project is violating stormwater rules.

Area
Missouri — statewide industrial stormwater policy
Decision stage
draft standard conditions — public comment
Next dated action
Aug 30, 2026
What to watch next

Review the draft and submit water-quality comments by 5 p.m. Aug. 30, 2026 if relevant. When evaluating a specific industrial development later, use the actual permit and site-specific stormwater requirements rather than assuming the statewide draft alone governs every activity.

Verification notes

Official Missouri DNR public notice. Standard Conditions Part 4 concerns industrial stormwater NPDES permits generally; the Reporter should link it to specific projects only when a project-specific permit or applicability record exists.

Open primary receipt ↗
Other

MoDOT awarded $807,191 for three Adair County resurfacing segments around Kirksville

The Missouri Highways and Transportation Commission awarded W. L. Miller Company an $807,191 resurfacing contract for Route H from LaHarpe Street to Missouri Route 11 in Kirksville, Route P from Business Route 63 to U.S. Route 63, and Route P from 0.3 mile east of U.S. Route 63 to Bass Way near Kirksville. MoDOT identifies the projects as part of the Governor’s Rural Roads Program funded through fiscal-year 2026 state general revenue.

Area
Kirksville and Adair County, Missouri
Decision stage
contract awarded; 2026 construction program
Next dated action
Date not stated in the source
What to watch next

Track construction dates, traffic impacts and final completion/cost records for the three segments. Do not report the $807,191 as the cost of any one segment because it is the combined contract amount.

Verification notes

Official MoDOT contract award. Combined contract amount applies to all three listed Adair County segments.

Open primary receipt ↗
Other

Missouri impaired-waters methodology public comment closes Aug. 14, 2026

Missouri DNR’s public comment period on the draft 2028 Section 303(d) Listing Methodology runs through Aug. 14, 2026. The methodology governs how DNR evaluates available data when deciding which Missouri waters are listed as impaired under the federal Clean Water Act. This is a statewide methodology process, not a finding that a particular Greentop or Schuyler County waterbody is impaired.

Area
Missouri — statewide water-quality policy
Decision stage
public comment closes Aug. 14, 2026
Next dated action
Aug 14, 2026
What to watch next

Submit written comments to Missouri DNR by the Aug. 14, 2026 deadline if the methodology affects a water-quality concern; then watch for Clean Water Commission consideration.

Verification notes

Official Missouri DNR public notice. Kept separate from local impairment claims because the notice concerns methodology statewide.

Open primary receipt ↗
Data Center

Missouri PSC adopts large-load protections intended to keep data-center costs with large customers

The Missouri Public Service Commission says Ameren Missouri and Evergy have approved large-load tariffs covering customers such as data centers. The PSC describes protections including long minimum service contracts, financial-security requirements, exit fees, minimum monthly billing and cost-stabilization recovery intended to prevent unjust or unreasonable large-load costs from shifting to residential and commercial customers. The PSC states Liberty’s large-load tariff case remains in progress.

Area
Missouri
Decision stage
Ameren and Evergy tariffs approved; Liberty case pending
Next dated action
Date not stated in the source
What to watch next

Use the applicable PSC tariff and utility-service territory when evaluating any proposed data center; continue watching the Liberty proceeding and future tariff revisions.

Verification notes

Official Missouri PSC source. This establishes statewide regulated-utility rate protections; it does not prove that any specific northeast Missouri data-center project exists.

Open primary receipt ↗
Other

Northeast Missouri aquifer mapping includes Schuyler and is expanding across the region

Missouri DNR’s Northeast Missouri Aquifer Characterization Project covers nine counties: Clark, Scotland, Schuyler, Lewis, Knox, Adair, Marion, Shelby and Macon. DNR says electromagnetic surveys began in 2025 in Clark, Scotland and Schuyler counties and expanded into Adair, Knox and Lewis in summer 2026. The project combines test holes, passive seismic work and airborne electromagnetic surveys to identify suspected buried-channel aquifers and possible potable groundwater sources. DNR says the survey data will be used to build a 3D hydrogeological framework and final report.

Area
Northeast Missouri
Decision stage
study and data analysis underway
Next dated action
Date not stated in the source
What to watch next

Watch Missouri DNR for the 3D hydrogeological framework, final report and any mapped groundwater findings relevant to local landowners and development planning.

Verification notes

Official Missouri DNR project page checked Aug. 14, 2026. DNR states the project began with electromagnetic surveys in Clark, Scotland and Schuyler counties and expanded into Adair, Knox and Lewis in summer 2026.

Open primary receipt ↗
Data Center

Missouri data-center energy and natural-resource review has two major 2026 milestones

Missouri DNR says it does not regulate data centers as a facility type; local governments are typically aware of proposed projects before DNR because DNR generally becomes involved when a project applies for an environmental permit. DNR is coordinating with the Public Service Commission on energy regulations and utility practices, and says data-center growth is expected to be the main driver of future Missouri energy-demand growth. A new State Energy Plan is due Sept. 1, 2026, and DNR says its broader data-center findings and recommendations are due to the Governor by Nov. 30, 2026. DNR also states that Missouri does not generally regulate the amount of in-state water use, although major water users capable of withdrawing at least 100,000 gallons per day must register and report annual use.

Area
Missouri statewide
Decision stage
state review and planning underway
Next dated action
Sep 1, 2026
What to watch next

Review the State Energy Plan when issued Sept. 1, then watch for DNR’s data-center findings and recommendations due Nov. 30, 2026. Local governments remain a key early source for proposed-project information.

Verification notes

Official Missouri DNR data-center guidance checked Aug. 14, 2026. The page identifies Sept. 1, 2026 and Nov. 30, 2026 state milestones and describes DNR permitting authority, water-use reporting and local-government relevance.

Open primary receipt ↗
Other

U.S. 63 conceptual study between Kirksville and Iowa line: final alternatives work underway

MoDOT is conducting a conceptual study of U.S. 63 between the Iowa state line and south of Kirksville. Public meetings and the May 12–25, 2026 comment period are complete, and final purpose-and-need/conceptual alternatives are in progress for fall 2026. MoDOT states there is currently no construction funding and no implementation timeline has been determined, so this should be treated as a planning study rather than an approved construction project.

Area
U.S. 63, Kirksville to Iowa state line
Decision stage
final conceptual alternatives in progress
Next dated action
Date not stated in the source
What to watch next

Watch MoDOT for the final purpose-and-need and conceptual alternatives expected in fall 2026; distinguish any recommended concept from a funded construction project.

Verification notes

Official MoDOT project page and April 29, 2026 public-meeting notice. MoDOT explicitly states no current construction funding and no implementation timeline.

Open primary receipt ↗