What is coming, who is doing the work, and what public money is involved?
Choose any Missouri county or search the documented projects. Each entry identifies its project area and original source.
12 of 12 researched project records shown · 11 of 115 county jurisdictions with records in this register · projects A–Z
Data Center · Montgomery County
Amazon — Montgomery City data-center campus
Stage: Announced plan; executed terms, permits and outcomes need checking
DED announced Amazon's $10 billion private investment plan in Montgomery City, with 400 direct jobs and thousands of construction jobs expected. Amazon announced more than $7 million in community contributions. These are commitments and forecasts, not verified public receipts or actual hires.
Records to check next: Find local agreements, incentive claims, contractor awards, employer vacancies and county receipts.
Evidence limits and research gaps
PRIMARY SOURCE: DED announcement, June 15, 2026; checked October 10, 2026.
MONEY: Private investment and company contributions announced; actual state tax benefit and local receipts unknown. DED says no electric-rate discount.
HIRING: Job figures projected; prime contractor and local-hire share unverified. No familial connection asserted.
Blevins Asphalt — Mount Vernon maintenance facility
Stage: Facility reported open April 27; actual hiring and benefit issuance unverified
DED reported Blevins Asphalt opened a 16,000-square-foot maintenance facility, with more than $2.8 million of company investment and two new jobs described. Its $28,002 Missouri Works figure is an estimate subject to verification, not a documented receipt.
Records to check next: Check Mount Vernon permits, building contractor, verified hires and Missouri Works issuance.
Evidence limits and research gaps
PRIMARY SOURCE: DED April 27 release, checked October 13, 2026.
STAGE: Facility reported open. Blevins is a paving contractor; the source does not name who built this facility.
HIRING: Two jobs described; verified payroll addition and local residence not established.
MONEY: More than $2.8 million company investment, $28,002 estimated Missouri Works benefit; actual issuance unknown.
GAPS: Building contractor, confirmed hires, public benefit issuance and decision-relevant family tie.
Stage: April expansion announcement; later job and benefit outcomes unverified
DED announced $125,000 private investment and two new jobs for a machine-shop expansion in Alton. It estimated $20,003 in Missouri Works benefits subject to verification and said personnel would be added in April. This dated announcement does not establish that the jobs were filled or the benefit issued.
Records to check next: Check actual hires, Missouri Works issuance and any facility procurement.
Evidence limits and research gaps
PRIMARY SOURCE: DED April 17 announcement; checked October 10, 2026.
MONEY: $20,003 conditional estimate, not an issued credit.
HIRING: Two positions announced; current vacancy or actual hire not verified. DED calls the company family-operated; no public-office family relationship is asserted.
Stage: Expansion announced; state benefit estimated; job and training outcomes open
DED announced up to $390 million of private investment, up to 123 new jobs and retention of 936 existing jobs. It estimated $5,603,531 in Missouri Works benefits subject to verification and said Missouri One Start assistance may occur. New jobs, retained positions and actually filled jobs are separate measures.
Records to check next: Obtain incentive issuance, any training award, job postings and actual new-hire/retention reports.
Evidence limits and research gaps
PRIMARY SOURCE: DED May 5 announcement; checked October 10, 2026.
MONEY: $5,603,531 conditional estimated Missouri Works benefit. Missouri One Start assistance is possible, not a verified award.
HIRING: Counts are projections and retention claims; current vacancies, contractors and worker residence not verified. No familial connection asserted.
DED announced 243 new jobs and reported active hiring across planning, production, maintenance, engineering and warehouse work. DED estimated $1,422,467 in Missouri Works benefits, subject to verification. The estimate is not issued tax credits or a payment received.
Records to check next: Check current employer vacancies, actual job outcomes and Missouri Works issuance.
Evidence limits and research gaps
PRIMARY SOURCE: DED July 15 announcement; checked October 10, 2026.
MONEY: $1,422,467 conditional estimated Missouri Works benefit, not actual issuance.
HIRING: DED reports active hiring; SRC Holdings links a career portal: https://www.srcholdings.com/genie-recon ↗ . Individual vacancies, contractors and local hires need checking. No familial connection asserted.
Stage: Announced facility and statewide investment; project-specific awards and outcomes open
DED says Google's $15 billion Missouri infrastructure announcement includes a New Florence data center. The amount spans Missouri infrastructure, not just this county. Thousands of construction jobs and hundreds of ongoing jobs are projected. A laborers' training partnership is documented, but hiring outcomes are not.
Records to check next: Match permits, agreements, prime contractor, training outcomes and actual local payments.
Evidence limits and research gaps
PRIMARY SOURCE: DED announcement, May 20, 2026; checked October 10, 2026.
MONEY: $15 billion is statewide announced private investment. Actual exemptions and receipts not established here; see Montgomery County money file for separately labeled PSC projections.
HIRING: Training targets are not hired-worker counts. Contractor and workforce residence unverified. No familial connection asserted.
Jarrell Contracting — Hazelwood headquarters and operations center
Stage: Expansion announced September 2; construction and completed hiring unverified
DED announced Jarrell Contracting's plan for a 191,000-square-foot headquarters and operations center and 105 new jobs. The $5,188,632 Missouri Works figure is an estimate subject to verification, not a received amount. Its St. Louis-area job postings are not identified as expansion-specific.
Records to check next: Check Hazelwood permits and building awards, expansion-specific hires, and Missouri Works issuance.
Evidence limits and research gaps
PRIMARY SOURCES: DED September 2 release and employer careers page, checked October 13, 2026.
MONEY: $5,188,632 estimated Missouri Works benefit subject to requirements; private investment amount and actual issuance not given here.
GAPS: Building contractor and subcontractors, actual hiring, issued benefits and decision-relevant family tie. Jarrell's mechanical contracting business does not establish that it is the builder.
King Technology — St. Peters manufacturing and distribution center
Stage: Facility open September 29; current employer postings; hiring total and benefit issuance unknown
DED reports King Technology opened a 208,000-square-foot facility, with at least $17 million in company investment. Its expectation of 40 workers within three years is not a confirmed hire count. The employer listed three Missouri openings October 13. Missouri Works support is conditional; an issued amount is unverified.
Records to check next: Check St. Peters agreements, construction contractor, verified staffing, and Missouri Works issuance.
Evidence limits and research gaps
PRIMARY SOURCES: DED September 29 release and King Technology careers page, checked October 13, 2026.
HIRING: Material Coordinator, Senior Manufacturing Process Engineer, and Shipping and Receiving Coordinator listed in Missouri; exact worksites unspecified. https://www.kingtechnology.com/work-with-us/ ↗
MONEY: At least $17 million reported company investment. Missouri Works conditional; no amount or issuance identified. Missouri One Start assistance is possible, not recorded as received.
GAPS: Contractor, local hire count, executed local terms, actual benefits and decision-relevant family tie unverified.
La-Z-Boy — Neosho manufacturing and distribution expansion
Stage: Expansion and new facility announced; benefit estimated, hiring outcomes open
DED announced $23 million of private investment and up to 100 new jobs in Neosho. It estimated $356,304 in Missouri Works benefits subject to verification, linked the employer's Neosho career search and reported a $20/hour starting rate at the existing plant. Live vacancy count and completed hires have not been verified.
Records to check next: Check employer postings, construction contractor, actual benefit issuance and hiring outcomes.
Evidence limits and research gaps
PRIMARY SOURCE: DED August 31 announcement; checked October 10, 2026.
MONEY: $23 million private investment announced; $356,304 estimated Missouri Works benefit, not issued amount.
Stage: Announced plan and state exemption program; actual benefit and hires unknown
DED announced a planned $1.4 billion Liberty campus with at least 30 ongoing jobs and hundreds of construction jobs expected. DED says Metrobloks will benefit from the Data Center Sales Tax Exemption Program; it does not quantify the exemption or identify a prime contractor.
Records to check next: Obtain exemption authorization and annual claims, city agreement, permit contractor and dated vacancies.
Evidence limits and research gaps
PRIMARY SOURCE: DED announcement, March 24, 2026; checked October 10, 2026.
MONEY: $1.4 billion private investment plan; actual exempted taxes not given.
HIRING: 30 ongoing and hundreds of construction roles are forecasts. Contractors and local-hire share unverified. No familial connection asserted.
Stage: First phase under construction; company-reported Chapter 100 approval; actual payments open
DED reports the first phase broke ground May 12. Nebius projects about 1,200 construction jobs, mostly local union trades, and 130 ongoing jobs at full operation. Nebius says Independence approved a Chapter 100 plan and projects more than $650 million in payments in lieu of taxes over 20 years; these are future projections, not receipts already collected.
Records to check next: Check the executed city agreement, PILOT receipts and trade contracts; Nebius careers lists Independence openings.
Evidence limits and research gaps
PRIMARY SOURCES: DED May 12 groundbreaking; Nebius March 3 statement; checked October 10, 2026.
Stage: Groundbreaking reported October 2; benefit amount and outcomes unknown
DED reported an October 2 groundbreaking, more than $19 million of planned private investment and 24 new jobs. It says Missouri Works will benefit the project subject to verification, but gives no dollar amount. Prime contractor, actual incentive issuance and completed local hires remain open.
Records to check next: Check permits, contractor awards, employer openings and Missouri Works authorization and issuance.
Evidence limits and research gaps
PRIMARY SOURCE: DED October 2 announcement; checked October 10, 2026.
MONEY: More than $19 million private investment announced; program eligibility described, no dollar estimate or issuance established.
HIRING: 24 jobs projected; vacancies and hires unverified. Prime contractor and familial connections not established.
Each record separates announcement, application, approval, award, construction, hiring and completion. Investment and job counts in announcements are projections until an outcome record confirms them. A tax credit estimate or eligibility statement is not an issued credit or a payment received.
For money, follow the state incentive authorization, tax-credit issuance or sales-tax exemption, local development agreement, payment in lieu of taxes, grant, contract and actual receipt. For work, identify the project sponsor, prime contractor, subcontractors, union or nonunion trade, actual recruitment and local hiring from dated original records. An employer headquarters or a job projection cannot establish where workers live.
Family or business relationships are reviewed only when relevant to a documented decision or contract, using official financial disclosures, business filings, campaign reports, votes, recusals and procurement records. Shared surnames and associations do not establish influence or misconduct. Sensitive or unverified personal leads do not appear in this directory. Search documented relationships only when relevant.